Choose the time measure before starting the clock
To find average elapsed time per good bent part, divide the elapsed time of a defined batch by its final accepted quantity. Count setup, first-piece approval, waiting and rework according to the agreed batch boundary. Record direct labor separately.
A single bend action, a complete part cycle and a batch average describe different things. A complete part may require picking, positioning, rotating, turning over, several forming actions and unloading. The batch also contains work that is shared across its parts.
| Measure | How to obtain it | Use |
|---|---|---|
| Complete part cycle | Time a part between defined process start and finish points. | Understand the repeated work on that part. |
| Batch-average elapsed time per good part | Batch elapsed time divided by accepted parts. | Include shared preparation and production losses within the chosen scope. |
| Direct labor per good part | Total person-time assigned to the batch divided by accepted parts. | Understand the labor input required for the output. |
The first result is a batch average. It is not the residence time of every individual part, the machine's occupied time or the full order lead time unless your chosen boundary explicitly describes that scope.
Define a closed batch and its acceptance point
For this worksheet, a practical start is the beginning of setup for the batch after the previous job releases the work area. Finish when all pieces in the recorded batch have a final disposition and the required inspection is complete. State any different boundary before comparing results.
Include all waiting within that interval and identify its cause. If inspection continues away from the machine after forming ends, this batch measure includes that elapsed period. It should not be interpreted as machine occupancy during that whole time.
Record programming or preparation completed before the start separately. State whether it is included in the labor total; it is not added to the elapsed interval again. Compare a new-part launch with another new-part launch, or a repeat order with a similarly prepared repeat order.
Define “good” using the drawing and the next operation. Relevant checks may include bend angles, flange dimensions, hole locations, surface condition and assembly fit. Agree on the inspection method and frequency.
Count an accepted first piece once if it is part of the deliverable batch. Count a reworked part once when it passes final acceptance. Keep scrap and pending decisions separate. Close the batch before reporting a completed-batch average.
Separate setup, first-piece work and the repeated cycle
Use an event log to explain where time goes. Give each record a start, finish, resource and activity. The following categories keep the main losses visible.
| Category | Record | Counting rule |
|---|---|---|
| Setup | Program preparation at the cell, tools, gripping arrangement and backgauge setup. | Separate work completed before the batch clock starts. |
| First piece | Trial forming, measurement, adjustment and approval. | If recorded as one stage, do not add its internal actions again. |
| Handling | Picking, supporting, turning over, rotating, repositioning and placing. | Identify actions that overlap machine motion. |
| Forming | The defined machine cycle or forming sequence. | State whether it includes approach, return, clamping and positioning. |
| Inspection | Routine production checks and acceptance. | Record off-machine or parallel inspection explicitly. |
| Rework | Correction, extra handling, repeat forming and reinspection. | Keep the original part ID; avoid duplicate accepted counts. |
| Waiting | Material, people, decisions, interruptions or faults. | Retain the time and its reason. |
During manual holding, the operator and machine may work on the same part simultaneously. Record what each resource is doing. Use batch start and finish timestamps for elapsed time; add event durations only when they are mutually exclusive and cover the interval completely.
Account for work that happens in parallel
In a suitable cell, the machine may form one piece while an operator prepares the next and another person checks an earlier piece. Those activities occupy the same clock interval. Their durations cannot all be added to obtain batch elapsed time.
In this illustrative window, the clock advances 10 minutes. The two people contribute 6 + 4 = 10 person-minutes. Adding the machine's 10 minutes to those labor activities would give an incorrect elapsed total of 20 minutes.
For each person, count their working intervals once. Supporting a part during a bend does not create a second labor interval for that same person. Add the recorded contributions of different people, and allocate shared staff to the work they actually perform for this batch.
Distinguish direct work from paid attendance or staffing commitments. If someone must remain assigned to the cell while waiting, record that requirement separately for a staffing or cost study.
A worked batch: 100 blanks and 96 accepted parts
This teaching example uses invented, non-overlapping stage times. It is not a GWEIKE machine test or a comparison between machine models.
Of 100 blanks, 90 pass first time. Eight enter rework; six recover and two become scrap. Two other blanks are scrapped directly. The closed batch therefore contains 96 accepted parts and 4 scrap parts, with no pending decisions.
| Non-overlapping stage | Minutes |
|---|---|
| Setup | 20 |
| First-piece forming, adjustment and approval | 12 |
| Production handling, turning and positioning | 32 |
| Production forming cycles | 18 |
| Production inspection | 10 |
| Rework and reinspection | 6 |
| Waiting | 2 |
| Batch elapsed time | 100 |
The production rows exclude actions already counted in the first-piece and rework stages. All first-piece blanks are included in the 100-piece input; the accepted first piece is included in the first-pass total.
If separately recorded direct labor totals 95 person-minutes:
95 × 60 ÷ 96 ≈ 59.4 labor seconds per good partSetup alone contributes 20 × 60 ÷ 96 = 12.5 seconds per accepted part in this example. Changing the batch size changes that allocation. Estimate the new batch from its own setup, production and quality records rather than scaling the whole result mechanically.
These values need not match. The accepted quantity already reflects the batch's scrap losses, so do not divide the result by yield again. If the order requires 100 good pieces, this example batch falls four short; extra production must be recorded before claiming the order is complete.
Fill in your bending batch record
Record a closed batch using the same boundaries for each route. The calculator uses start and finish timestamps for elapsed time. Event rows explain activities and are not summed into that interval.
Print or save a copy before closing this page. Reloading clears unsaved entries. “Load worked example” replaces entries with the teaching example above.
Compare manual holding and automatic bending on the same task
Confirm that both routes can produce the required part before comparing time. Review material, thickness, flange geometry, final-side clearance, gripping areas and tooling. Include any additional operation needed by either route to deliver the same accepted result.
Manual holding on a CNC press brake
Observe the work between bends: pickup, support, orientation, backgauge contact, turning and placement. A manually held workpiece can still be processed on a CNC press brake. The GWK 13032 demonstration provides examples of handling and forming to identify in the log.

For this route, evaluate tooling preparation, backgauge use and operator support alongside the forming cycle. Review the HG Series CNC press brake with your actual part sequence and batch record.
Panel bending and automated handling
Identify the machine-controlled gripping, rotation and forming actions. Then record replenishment, program preparation, first-piece checks, unloading and exception recovery that remain outside the demonstrated sequence.
The GKS-BC0315 demonstration shows panel-bending actions. The GWEIKE automated bending clip illustrates another handling arrangement. Neither edited clip provides a complete batch record for your own production.

A published time per bend needs its action boundaries and conditions confirmed. It cannot be multiplied by the bend count to establish the full accepted-part cycle. Check the suction-cup panel bender or press-arm panel bender against the part's gripping and forming requirements.
Use the same drawing revision, material requirements, acceptance criteria and clearly stated quantity basis. For an order-completion comparison, target the same accepted quantity and record the blanks consumed. Keep new-part preparation separate from repeat-order performance.
Batch size changes how shared preparation is distributed. A repeatable tooling plan can help a press brake; suitable automatic setup can also support changing jobs on a panel bender. Measure the proposed configurations rather than assigning each process a universal minimum batch size.
Use the record to choose the next improvement
| Largest loss | What to investigate |
|---|---|
| Setup and program preparation | Tool organization, verified programs, setup plans and suitable changeover functions. |
| Handling and repositioning | Part support, bend sequence, gripping feasibility and automatic handling options. |
| First-piece adjustments or rework | Material consistency, tooling, springback compensation and measurement method. |
| Inspection or output congestion | Inspection allocation, discharge space and the next operation's ability to receive parts. |
A shorter bend action helps only the relevant part of the record. Retain quality results and elapsed time together when reviewing an improvement. A faster sequence that adds correction or inspection work may deliver less benefit than the selected clip suggests.
Repeat the observation on representative orders. Keep the normal interruptions and explain unusual ones. Use the resulting range and job mix for planning instead of turning a single best run into a factory-wide promise.
Review your bending route with a batch record
Send GWEIKE your part drawing, material and thickness, normal quantity, quality requirements and completed timing record. Include the current tooling, holding method and any additional operations.
Ask for a proposed CNC press brake or panel-bending configuration and a trial with agreed boundaries, accepted quantities and labor records.