Which duct parts actually go to the laser?
Start with the fittings on the cut list. If a dedicated line already shears and forms your straight rectangular duct, leave that tonnage off the laser purchase calculation. Count the flat patterns the laser would actually cut, such as elbow cheeks, throats and heels, transition panels and offset sections. Keep the job number with each pattern so you can tell when the last piece of a fitting is ready.
Monday’s repeat order is a strong candidate for coil feeding if the blanks fit the strip and there is enough work in the same stock to keep it running. For Tuesday’s short order, sheets already on the rack may get the whole kit to forming sooner. Look at how long one material specification can stay on the machine and which piece the forming crew will be waiting for.
When does coil feeding make sense?
Look at the unfolded transition, including its seam and flange allowances. Compare its widest dimension with the usable strip width after the edge margins. Even a roll with plenty of length can leave a strip of waste down one side. Try turning alternate blanks if the drawing, surface finish and forming direction allow it.
Now check the work behind Monday’s forty transitions. Elbow cheeks for another job might fit beside those panels and run from the same coil. They can differ in shape and still share a nest if grade, coating, thickness and due dates agree. Give each loose piece a job and fitting ID before mixing orders. Otherwise the gain at the cutter may turn into a search for matching pieces at the folder.

On a trial, watch the operator thread the coil, set the leveler and check the first blank on a flat surface. Take a long panel to the forming station and check that its seam edges line up after folding. If coil handling is new to your shop, the coil laser cutting guide explains the equipment between the roll and the cutting bed.
The GWEIKE CPL coil width and thickness specifications list 500–1,500 mm coil widths for the GKS-CPL3015B and GKS-CPLS6015B, with 0.8–3 mm carbon steel and 0.8–2 mm stainless steel. For galvanized duct stock, send the actual thickness and coating designation for confirmation and a sample cut. The published table gives no separate galvanized range.
When do cut-to-length sheets fit the order better?
For Tuesday’s elbows and offsets, pull the cut list apart by thickness. If two cheeks can come out of a tagged remnant and the other blanks fit sheets on the rack, the crew can finish one installation without waiting for another order to fill a coil nest. Check that the remnant has the right coating, is traceable to the required material, and can be held and cut on the proposed bed.
How quickly can the operator switch between Tuesday’s three thicknesses? A line with several coils already staged may switch stock quickly. Time the change from the last good blank of one thickness to the first good blank of the next. Apply the same clock to the sheet route, including retrieval, sheet separation and alignment. That comparison can favor either route.

Size a sheet-fed laser cutting machine around the largest unfolded blank and the stock you buy. If loading whole sheets is the measured delay, check the loader separately. For example, the GAS automatic sheet loading system lists a minimum handling thickness of 1 mm and a minimum sheet size of 2,000 × 1,000 mm. A 0.7 mm sheet is outside that loader’s published range, regardless of the laser’s cutting capability.
Nest the same fittings on coil and sheet
Ask for two nests made from the same DXF revision. Keep seam allowances, edge clearance, gaps, rotation rules and quantities the same. Give the programmer the coil widths and sheet sizes you can actually buy. A comparison against a width that your steel supplier does not stock will tell you little about next month’s material bill.
Five transitions from Monday’s order
In this simplified layout, four panels across a 1,250 mm strip make one transition kit. Each row occupies 580 mm along the feed. Allow 20 mm between rows and 25 mm at either end. The blue shapes are the four panels, each at most 290 mm wide including its seam allowance. The gold area is a potential remnant. Actual DXF nests must include the seam details and any machine-specific trim.
Coil · five kits in one strip
Sheets · four kits on the first sheet, one on the second
Five kits need 3,030 mm of coil in this layout (5 × 580 mm + 4 × 20 mm + 2 × 25 mm). Four rows fit on one 2,500 mm sheet. The fifth starts a second sheet. With the same margins, up to 1,870 mm of its full width can be set aside as a remnant before any cut-off allowance. Credit that material when it returns to a job. On the coil, record any additional length lost to threading, trimming or the tail when the roll is changed.
Repeat the calculation for all forty kits. The same pattern takes 24.03 m of strip before any coil-change losses, versus ten full sheets totaling 25 m at the same width. All ten sheets carry four kits. That nearly empty second sheet in the five-kit example tells you very little about the economics of the full order.
Time one complete fitting kit through to forming
A pile of cut blanks can make the laser look productive while the folder waits for one missing cheek. Start the trial when the operator begins retrieving or changing stock. Stop when the last required blank has passed inspection, carries its fitting ID and reaches the agreed forming station. Check a trial assembly for seam engagement, matched edges and correct handedness before counting a kit as good.
- Clock time per complete kit. Divide elapsed batch minutes by the number of complete, accepted kits delivered. Include sorting, waiting and recuts. When cutting and unloading overlap, count those minutes once.
- Material per kit. For each gauge, record the coil width and length consumed or the sheets issued. Track reusable remnants and scrap separately. Compare costs using the shop’s delivered stock prices and its normal credit for material returned to inventory.
- Missing or rejected pieces. Record which fitting they held up and why. If an offset side was cut in the wrong hand, the remaining pieces stay on hold until its replacement arrives.
For Monday, look for a run long enough to spread the coil setup across forty complete transitions. For Tuesday, check the time at which all eight fittings for the installation can leave together. If every piece is already waiting at a busy folder, extra laser capacity alone will not bring that shipment forward.
Compare both feed methods on your duct drawings
Send GWEIKE a repeat fitting order and a mixed installation order. Include the unfolded DXFs, panel quantities per fitting, material grade, coating, actual thickness, available coil widths and standard sheet sizes. Mark any faces that must stay outward and any blanks that cannot be rotated.
Ask for both nests, the stock consumed, the reusable remnants and the elapsed time to deliver one complete batch to forming. Those records let you compare the two routes against your own prices and dispatch schedule.
Request a coil and sheet trial on your DXFs