Workshop Readiness • Installation Checklist • GA Series

Fiber Laser Cutter Installation Requirements Checklist

Use this page to validate your workshop before delivery: space & access, foundation, utilities (power/grounding), assist gas, ventilation, rigging/unloading, and commissioning. Values and constraints referenced from GA Series user manual and may vary by exact model & local codes.

For enclosed exchange-table fiber laser cutters Site + utilities + safety + rigging Procurement-friendly checklist tables

How to use this checklist

Treat this as a “work order” for your facilities team and an “acceptance gate” for procurement: everything marked Must-have should be done before the machine arrives.

Model-specific drawings still matter
GA models (3015/4020/6015/6020/6025/8025) have different footprints and anchor layouts. Use this checklist for the common requirements, then confirm the final foundation drawing for your model.
Don’t “assume” utilities
Most commissioning delays come from missing gas regulators, wrong water type, or unstable power. Lock these in at least 2–3 weeks before delivery.
GA Series Fiber Laser Cutter Installation Requirements Checklist

Phase 0: Before delivery (access & route)

Plan the machine’s route from truck → door → final bay. Confirm clearances and overhead constraints.

Route & access checks

  • Confirm door opening size, pillar height, cable holder height, and whether the road surface can support armored rollers/rigging.
  • Pre-plan any floor works (slitting/punching etc.) per the basic plan before the machine arrives.
Tip: If you have tight doorways or low overhead beams, do a “dry run” with your rigging contractor using the final footprint drawing.

Video

Watch the GA Series customer feedback and workflow context.

Phase 1: Space planning & environment

Minimum service clearance

Keep enough room for maintenance access, exchange table movement, and safe material handling.

  • Leave ≥1.2 m at the left and rear sides of the machine tool.
  • Keep the laser and water chiller1.0 m from the wall.

Environmental constraints

  • Use a site with good ventilation; avoid dust/corrosion/pollution/water leakage; recommended ambient temperature +5°C to +45°C.
  • Avoid thermal deformation from one side in direct sunlight and the other side in wind (consider louvers if near windows).
  • Avoid strong electromagnetic interference sources (arc welding, EDM) near control/servo units.

Phase 2: Floor & foundation requirements

Floor performance (baseline)

  • Ground flatness: ±10 mm.
  • Concrete thickness under bed & legs: ≥200 mm; compressive strength ≥30 N/mm²; load >30 kN/m².
  • Foundation installation should avoid large vibrations; if present, drill a shock ditch.

Embedded steel plates & anchors (example method)

  • Embed steel plates at ground level; steel plate thickness ≥20 mm, size 200×200 mm.
  • Example anchor method uses expansion bolts M12×100 (quantity shown as 64 in the example instruction).
  • Some sites may pour concrete columns (example size 400×400×600) for base anchors; strong cement surfaces may be used directly as foundation.
Engineering note: Always validate against your local building codes and the final GA model foundation drawing.

Phase 3: Power quality & grounding

Electrical supply & quality

  • Electrical spec reference: Three-phase five-wire, 380V 50Hz (frequency may vary by model).
  • Power quality: three-phase unbalance <2.5%, line voltage fluctuation <5%; single-phase 220V ±5%.
  • Use a regulated power supply for machine/laser stability; avoid routing air compressors/fans through the regulator.

Grounding requirements

  • Grounding resistance should be <4 Ω.
  • Ground needles: total ≥3; material pure copper or galvanized; diameter ≥15 mm; length ≥1.5 m (set about 1 m away from machine).

Typical procurement list (reference)

Below items are commonly prepared before installation (air switches, stabilizer size, power cord spec, etc.). Confirm with your final laser power and local electrician.

Item Reference spec Notes
Distilled/Purified water 18 L/barrel; chiller water volume: 1–1.5 kW: 15 L; 2–3 kW: 25 L; 4–6 kW: 50 L Mineral water prohibited.
Machine air switch 4P/AC380V; 1–2 kW: 63A; 3–6 kW: 80A Reference values.
Voltage stabilizer AC380V; 1–4 kW: 30 kVA; 6 kW: 50 kVA Reference values.
Main power cord 5P; 3–5 m; cable spec: 1–2 kW: 6 mm²; 3–4 kW: 10 mm²; 6 kW: 16 mm² Reference values.
Leakage protection note Recommend air switches without leakage protection; if used, leakage current ≥300 mA (recommended >500 mA) To reduce nuisance trips.

Phase 4: Assist gas standards & piping

Gas purity & supply logic

  • Oxygen: purity >99.6%; if using liquid oxygen, add vaporizer; example output pressure 1.0 MPa and flow 1.0 m³/min (reference).
  • Nitrogen: purity ≥99.99%; if using liquid nitrogen, add vaporizer; example output pressure 2.0 MPa; flow reference: 1.5 m³/min (≤3 kW) / 2.2 m³/min (>3 kW).
  • Air cutting: requires pure and dry high-pressure air; max air pressure 3.0 MPa.
  • Do not use gas cylinders completely; keep residual pressure (at least one atmosphere above air pressure) and replace gas when oxygen pressure is low to avoid alarms.

Regulators (reference)

Regulator Reference spec
Nitrogen pressure reducing valve Input ≥15 MPa; Output 0.2–3.0 MPa
Oxygen pressure reducing valve Input ≥15 MPa; Output 0.05–1.2 MPa
Implementation tip:
For higher power or heavy nitrogen usage, many factories move from cylinders to liquid tanks + vaporizers or on-site nitrogen generation. Confirm your “assist gas strategy” during quoting so facilities can prepare early.

Phase 5: Cooling water & winter prep

Water type

  • Cooling circulating water requires distilled water or purified water; mineral water is prohibited.

Below-freezing protection

  • When ambient temperature is below 0°C, use antifreeze (ethylene glycol or polypropylene glycol); alcohol/corrosive antifreeze is prohibited.
Best practice: Put “winter procedure” into your SOP (who drains, who replaces, who verifies chiller operation during power interruptions).

Phase 6: Ventilation, fume extraction & fire safety

Ventilation & extraction

  • Exhaust gas generated during cutting is harmful; ensure dust suction device is operating normally and the working site is ventilated.

Fire safety

  • Processing site should be equipped with appropriate fire extinguishers and reserve certain fire exits.
  • Oxygen cutting increases fire risk; remove flammable/explosive materials and maintain preventive facilities.
Operator safety reminder:
This is a Class IV laser system; implement PPE and access control rules in your workshop SOP.

Phase 7: Unloading & rigging tools

Prepare lifting and handling tools in advance. If your model is larger (e.g., 6025/8025), upgrade lifting capacity accordingly.

Required tools (reference)

  • Truck crane recommended ≥10 t lifting capacity (higher if boom needs are larger).
  • Forklift capacity 10 t; bridge crane bearing capacity 10 t.
  • At least 2 hydraulic jacks with lifting force ≥5 t (min height setting 30 mm); armored rollers; crowbar extensions.
  • If model is LF6025GA/LF8025GA, prepare 15 t lifting equipment.

Handling precautions

  • Do not place the machine on the floor without a bottom plate; keep bottom plate <100 mm from ground during movement.

Phase 8: Unpacking, installation & trial cutting

Unpacking & incoming inspection

  • Check product type, damage during transport, completeness of components; contact supplier if mismatch/missing/damage.

Typical engineer scope (what to expect)

  • Level adjustment; water chiller installation; fiber optic installation; cutting head installation; gas connection; fan installation.
  • Power-on test: external voltage, origin/limit switch tests, axis homing, chiller & fan power-on.
  • Trial cutting: air opening, red light check, nozzle adjustment, calibration/edge finding, parameter setting, cutting.
Acceptance gate: Don’t accept “it runs” — accept based on repeatable cut quality on your real parts/materials + stable alarms/pressure/temperature behavior.

Printable checklist table

Copy this table into your internal tracker (Excel/Notion). Columns are designed for facilities + procurement collaboration.

Checklist item Requirement / target Priority Owner / status
Service clearance Left & rear ≥1.2 m; laser/chiller ≥1.0 m from wall. Must Facilities: ☐ Planned ☐ Done
Floor flatness & slab Flatness ±10 mm; concrete thickness ≥200 mm; compressive strength ≥30 N/mm². Must Facilities: ☐ Test ☐ Done
Power supply 380V 50Hz 3-phase 5-wire; unbalance <2.5%, fluctuation <5%. Must Electrician: ☐ Verified
Grounding Grounding resistance <4 Ω; ≥3 ground needles; length ≥1.5 m; dia ≥15 mm. Must Electrician: ☐ Verified
Cooling water Distilled/purified water only; mineral water prohibited. Must Ops: ☐ Purchased
Assist gas O₂ purity >99.6%; N₂ purity ≥99.99%; prepare regulators and safe piping. Must Ops: ☐ Contracted
Ventilation & extraction Ensure dust suction works and workshop ventilation is adequate. Must EHS: ☐ Approved
Fire safety Fire extinguishers + clear fire exits; remove flammables near cutting area. Must EHS: ☐ Approved
Rigging tools 10t crane/forklift/bridge crane; 5t jacks; 15t lifting for LF6025GA/LF8025GA. Must Rigging vendor: ☐ Booked

FAQ

How much space do we need around the machine?

Reference clearance is ≥1.2 m at left and rear, and ≥1.0 m from the wall for the laser and water chiller.

What are the basic foundation requirements?

Reference requirement: ground flatness ±10 mm; concrete thickness ≥200 mm; compressive strength ≥30 N/mm²; load >30 kN/m².

What power quality and grounding do we need?

Reference: 380V 50Hz 3-phase 5-wire, three-phase unbalance <2.5%, line voltage fluctuation <5%, and grounding resistance <4 Ω with ≥3 ground needles.

What gas purity is recommended for oxygen and nitrogen cutting?

Reference: oxygen purity >99.6% and nitrogen purity ≥99.99%. Flow/pressure planning depends on laser power and your production strategy.

What water should we use in the chiller?

Use distilled water or purified water; mineral water is prohibited. For below-freezing environments, use appropriate antifreeze (ethylene glycol or polypropylene glycol), not alcohol-based fluids.

What lifting capacity do we need for unloading?

Reference recommends ≥10t lifting tools; for LF6025GA/LF8025GA, prepare 15t lifting equipment.

Want a site-readiness review before delivery?

Share your workshop layout (door/route), power specification, assist-gas plan, and ventilation concept. We’ll confirm key requirements for your GA Series configuration and help you avoid commissioning delays.